QSRA · MONTE CARLO · SUMMIT TOWER
SCENE 01 / 08 · INTRO
G. KAFKA · S.E.T · FOUNDATION DESIGN
QUANTITATIVE SCHEDULE RISK ANALYSIS · AACE RP 57R-09 · OPRA-COMPATIBLE

MONTE CARLO
SCHEDULE RISK

PROJECT SUMMIT TOWER · 41 FLOORS · 489 FT · NEWARK NJ
STRUCTURAL ENGINEERING · FOUNDATION DESIGN
GABE KAFKA · STRUCTURAL ENGINEERING TECHNOLOGIES (S.E.T)

Three-point triangular duration distributions over a 43-activity CPM network. Sampled durations propagate through a forward pass; the maximum early-finish defines the project completion for each iteration.

Iterations10,000
Activities43
WBS Groups9
Risks15
Baseline T
PRESS TO ADVANCE · SPACE TO PLAY · F FULLSCREEN · 1-8 JUMP
Summit Tower — 41-story residential tower, Newark NJ
SUMMIT TOWER · NEWARK NJ RENDERING

      
SCHEDULE · ACTIVITY NETWORK (44)
RISK PARAMETERS · THREE-POINT FACTORS (44)
DEFAULTS LOADED · SUMMIT TOWER
RISK REGISTER · SUMMIT TOWER · 15 IDENTIFIED RISKS SORTED BY PID DESC
DETERMINISTIC BASELINE GANTT · CPM FORWARD PASS T_DET = — DAYS
TRIANGULAR DURATION DISTRIBUTIONS · ONE PER ACTIVITY FILL = PDF · DASHED = MODE
Iterations0/ 10,000
Current Tworking days
T deterministicbaseline
Meandays
Std Devdays
P50median
P8080% conf
P9090% conf
LIVE GANTT · EACH ITERATION RESAMPLES DURATIONS, RE-RUNS FORWARD PASS DET (DASH) · CURRENT (SOLID) · GHOSTS (FAINT)
HISTOGRAM OF T N=0
S-CURVE (CDF) P50 / P80 / P90
HOVERED ACTIVITY — hover —
Iterationstotal
T deterministicdays
Det Confidencepercentile
Meandays
Std Devdays
P50median
P8080% conf
P9090% conf
EXPORT

PERCENTILE TABLE

PERCENTILEDAYSΔ FROM DETΔ %

INTERPRETATION

The deterministic baseline sits at only confidence, meaning a plan built on it has that much chance of delivering on time or early. For commitments use the P80 target of days.

The standard deviation of days reflects the compounding effect of risks propagating through the CPM network.

TORNADO · ACTIVITY SENSITIVITY (SPEARMAN RANK CORRELATION) TOP 15 DRIVERS
READY